| New Office Space and Move |
Description
Prepare for and support relocation of HAS building and staff, Housing Outreach Services staff (from 209 ADM) and Housing IT staff, including equipment and furniture from current locations to the new space in the Student Center
Details
Project Lead: |
Connie Malone, Director of Planning Research and Administration |
Project Timeline: |
Fall 2005 through Winter 2008 |
| Fall 2007 Status: | Phase I of the HAS, HIT, and HOS move to the Student Center (to Suites G458 and G465) was completed in September 2007. Phase II of the move, which will bring the Housing Cashiers, account counselors and operations staff over to the Student Center, will be completed in February 2008. |