Description
Renovation of 20 buildings (210 apartments) to address health, safety, code concerns, and chronic maintenance issues, modernize appearance and explore the possibility of increasing bed spaces. Rebuild the maintenance facility and the community center that was destroyed by fire in 2000.
Details
Project Lead: |
Beverly Chaney, Director, Verano Place Housing and Gail Caldwell, Associate Director, Operations--Verano Place Housing |
Project Timeline: |
Fall 2006 through Fall 2007 |
| Project Overview: | Link to Overview (PDF, 15kb) |
| Fall 2007 Status: | Project specifications have been developed and costs estimated. A preliminary PPG has been drafted with the Budget Office and Capital Planning. An FMR and proposed work plan has been submitted to Facilities Management for building 6100, which will serve as a prototype for the full project. |